Paver Crosswalk Reconstruction

Paver Crosswalk Reconstruction

Paver Crosswalk Reconstruction

Overview

This project replaced various brick crosswalks with stamped concrete to increase their longevity and improve safety and visibility at the following locations:

  • 1300 South and 1900 East
  • 200 West and South Temple
  • West Temple and South Temple
  • 100 South and Main Street
  • 300 West and South Temple
  • 150 South Main Street
  • 200 South Main Street

Investment

$122,000.00

Schedule

Design: December 2017
Contractor Selection: January 2018
Construction: March – April 2018

Contact Information

Project Manager: Eric Casperson (801) 535-7995, eric.casperson@slcgov.com
Civic Engagement Program Specialist: Adan Carrillo (801) 535-6251, adan.carrillo@slcgov.com