1700 South: 1700 East to 1900 East

Posted on: November 1st, 2018

Overview This street reconstruction project will replace the deteriorating asphalt with a concrete pavement to increase roadway longevity and safety for travelers. Other project features include bus pads,  and upgrades to access ramps and sidewalks to enhance travel experience for people walking and taking transit. A new storm drain system with new curbs and gutters […]

700 South: from 5550 West to 5600 West

Posted on: July 16th, 2018

Overview This roadway project reconstructed the asphalt pavement on this short segment of 700 South to improve travel safety and drainage and to increase roadway longevity. Project Map Schedule Design: spring 2018 Completion: June 2018 Contact Information Civic Engagement Specialist: Adan Carrillo (801) 535-6251, adan.carrillo@slcgov.com + Contacta Adan Carrillo si necesitas esta información en Español.  

1300 East: 1300 South to 2100 South

Posted on: June 28th, 2018

For more information please visit the project website at: http://www.slc.gov/mystreet/1300east/ This page is only a summary about the project. Overview This summer we began to replace and rehabilitate aging underground utility lines to improve water and sewer services as part of a two-year effort to reconstruct this segment of 1300 East. Once we complete this first phase of […]

Simpson Avenue: Wyoming Street to Broadmoor Street

Posted on: June 27th, 2018

Overview This roadway reconstruction project replaced the deteriorating asphalt with a concrete pavement to increase its longevity and safety. Other project features included upgrades to pedestrian ramps, sidewalks, curb and gutter to improve walkability and drainage. Schedule Design: early 2018 Contractor Selection: spring 2018 Project Completion: spring 2018 Contact Information Civic Engagement Program Specialist: Adan Carrillo […]

Wilmington Avenue: 2000 East to 2100 East

Posted on: June 27th, 2018

Overview This roadway reconstruction project replaced the deteriorating asphalt with a concrete pavement to increase its longevity and safety for travelers. Other project features included upgrades to pedestrian ramps, curb and gutter to improve walkability and drainage in the neighborhood. Schedule Design: Winter 2017 Contractor Selection: Spring 2018 Project Completion: Summer 2018 Contact Information Civic […]

2100 East: 1700 South to Parkway Avenue

Posted on: June 27th, 2018

  Overview This pavement reconstruction project replaced the deteriorating asphalt to increase roadway longevity and safety for travelers. Other project features included upgrades to pedestrian ramps and new pavement markings to improve access and travel experience. Schedule Design: early 2018 Contractor Selection: spring 2018 Project Completion: summer 2018 Project Photos Before After Contact Information Civic […]

1500 East: 900 South to 1300 South

Posted on: June 27th, 2018

  Overview This project reconstructed the asphalt pavement along this segment of 1500 East to increase roadway longevity and safety for travelers. Other project features included new pavement markings and upgrades to access ramps and curb and gutter to improve travel experience and drainage conditions. Project Map Project Photos Before After Schedule Design: early 2018 Contractor […]

Wilmington Avenue: Highland Drive to 1300 East

Posted on: June 27th, 2018

Overview This roadway project reconstructed the deteriorating asphalt pavement with concrete to increase its longevity and safety. Other project features included a new sewer line, as well as crosswalks, access ramps and sidewalks with curb and gutter to improve walkability and drainage.   Investment $550,000 Schedule Design: winter 2017 Contractor Selection: spring 2018 Project Completion: […]

Paver Crosswalk Reconstruction

Posted on: June 27th, 2018

Overview This project replaced various brick crosswalks with stamped concrete to increase their longevity and improve safety and visibility at the following locations: 1300 South and 1900 East 200 West and South Temple West Temple and South Temple 100 South and Main Street 300 West and South Temple 150 South Main Street 200 South Main […]

1200 East: 600 South to 800 South

Posted on: June 27th, 2018

Overview This project installed a raised median to improve safety, mobility and predictability in the neighborhood. As part of the project, crews also resurfaced the pavement with new asphalt to prolong its longevity. The new median is a continuation of the one between 300 South and 500 South, and it will improve access and aesthetics […]