1200 East: 600 South to 800 South

New raised median along 1200 East between 600 South and 800 South

Overview

This project installed a raised median to improve safety, mobility and predictability in the neighborhood. As part of the project, crews also resurfaced the pavement with new asphalt to prolong its longevity. The new median is a continuation of the one between 300 South and 500 South, and it will improve access and aesthetics in the area.

Investment

$500,000

Schedule

Design:  winter 2017
Contractor Selection: spring 2018
Construction: summer 2018
 

Project Photos

Contact Information

Project Manager: Eric Casperson (801) 535-7995, eric.casperson@slcgov.com
Civic Engagement Program Specialist: Adan Carrillo (801) 535-6251, adan.carrillo@slcgov.com