Wilmington Avenue Reconstruction (Highland Drive to 1300 East)

Responsive Margin

You are viewing archived content. This content is no longer updated and links may not work.

Overview

The Wilmington Avenue reconstruction project, from Highland Drive to 1300 East, replaced deteriorating asphalt with concrete pavement to improve roadway longevity and safety. The project also included installation of a new sewer line, along with new crosswalks, upgraded access ramps, sidewalks, and curbs and gutters to improve walkability and drainage. The project was designed in winter 2017 and completed in June 2018.

Construction crews rebuilding Wilmington Avenue.
Construction crews rebuilding Wilmington Avenue.
Construction crews rebuilding Wilmington Avenue.
A person on a bicycle crossing Wilmington Avenue