In 2020, Salt Lake City reconstructed 700 West between 1600 South and 2100 South to extend the roadway’s lifespan through this busy industrial area west of I-15.

The project included new asphalt, curb and gutter for improved drainage, and new sidewalks and pedestrian ramps to enhance safety and comfort. Drive approaches were also added to better define sidewalks and access to nearby businesses and warehouses.

Project map

A map of the 700 West reconstruction project corridor.

Before and after

Deteriorated pavement on 700 West prior to the reconstruction project.
700 West prior to reconstruction
Smooth pavement on 700 West following the reconstruction project.
700 West following reconstruction

Funding

This project at the time of reconstruction was valued at $2 million, and was constructed via the Funding Our Future Street Reconstruction Bond approved by voters in November 2018.

Timeline

Design: Fall 2019

Construction: Spring to fall 2020

Project completion: 2020