Post Street & 1000 West: 700 South to 800 South

Responsive Margin

Overview

In 2019, Salt Lake City combined the reconstruction of Post Street and 1000 West (from 700 South to 800 South) into a single project to streamline the schedule, maximize resources, and minimize disruption for nearby residents. Improvements included new pavement, upgraded access ramps, and repairs to curbs, gutters, sidewalks, and drive approaches.

Project map

Map showing the 2019 reconstruction project limits on Post Street and 1000 West between 700 South and 800 South in Salt Lake City. Highlighted segments indicate the areas improved as part of a combined street reconstruction effort.

Funding

This project was made possible with a $550,000 investment from Community Development Block Grant (CDBG) funds.

Informational resources

Before and after

View of 1000 West before reconstruction, showing cracked and deteriorated pavement, snow patches on lawns, and parked cars lining the curb.
1000 West prior to reconstruction.
Reconstructed section of 1000 West showing smooth new concrete pavement, green lawns, mature trees, and parked vehicles along a quiet residential street under a sunny blue sky.
1000 West following reconstruction.