Capital Improvement Program (CIP)

The City Council has approved CIP Funding for FY26.

The Constituent application window for FY27 is now closed. Although the FY27 process has closed, we urge you to apply during our next round. A link for FY28 applications will be available on our website in the Fall of 2026.

Oprima en esta oración para leer la información en español.

What is the Capital Improvement Program (CIP)?

Salt Lake City’s Capital Improvement Program (CIP) is a multi-year planning program of capital expenditures needed to replace or expand the City’s public infrastructure. In other words, CIP pays for big projects like parks, public buildings, and street projects. Have a street, sidewalk, or curb and gutter issue? Please check MyStreet Services for help. 

Capital improvements involve the design, construction, purchase or rehabilitation of the City’s infrastructure including buildings, parks, streets, sidewalks, bridges, transportation features, traffic signals or other physical structures.

A capital improvement must have a useful life of five or more years, have a minimum cost of $50,000, and satisfy the functionality of a capital asset.

Each budget year, money is set aside for CIP. The City Council reviews the CIP plan during the annual budget process and approves the total amount of available funding. Over the summer, the Council further reviews and appropriates project-specific funding. Learn more about the Council’s role in CIP here.


What is a constituent request? Who can submit one?

Residents, neighborhood groups, community-based organizations, or neighborhood business district organizations of Salt Lake City are able to participate in the CIP process by submitting constituent request applications. See the latest information in the “Constituent Request Applications” section below.

Constituent Request Applications

If you are a resident, neighborhood group, community-based organization, or neighborhood business district organization of Salt Lake City and are interested in applying you must complete the ZoomGrants application.

Salt Lake City welcomes and values community input for potential capital improvements throughout the city. Once submitted, constituent request applications are forwarded to the appropriate City Department/Division to evaluate for specific criteria and the alignment with the Department/Division or City’s master plans. During this process, City staff will continue to collaborate with the applicants concerning the project scope and cost estimates.

Please note: The constituent request application deadline is not the final application submission deadline. Internal Department/Divisions will continue collaborating with constituents until the final application deadline in late December.

Constituent Request Application Criteria:

  • The capital project must have a cost estimate of at least $50,000 (for city infrastructure projects, cost estimates must be performed by Salt Lake City’s Engineering Division)
  • The capital project must have a useful life of 5 or more years
  • The capital project must be a Salt Lake City-owned asset
  • Community Outreach or Alternative Public Engagement is required
  • Locate your District, Community Council, and City Council Member with this interactive map

If you have questions or need assistance filling out the application, please contact [email protected].

CIP Timeline

Salt Lake City Capital Improvement Program (CIP) — Yearly Timeline
A yearly timeline showing three parallel tracks — Funding Process, Constituent Requests, and City Divisions — each broken out by month from January through December, describing who is responsible for each phase of the Capital Improvement Program.
Jan
Feb
March
April
May
June
July
Aug
Sep
Oct
Nov
Dec
Funding
Process
CDCIP Board
Mayor
City Council
Applications Due
Board reviews and recommends projects
Mayor reviews and recommends projects
Creation of Mayor’s Recommended Budget
City Council reviews and allocates funds for projects
City Council approves project-specific budgets
Applications due at the end of the month
Constituent
Requests
Constituents
Constituents with City Divisions
Requests due at the end of the month
Constituents work with a City Division on their Constituent Request
City
Divisions
City Divisions
City Divisions with Constituents
Design and construction work for approved and active projects
City Divisions work with Constituents on the Constituent Request

Notes:

  • Projects take at least one year to go through the CIP process, from pre-submittal to allocation
  • The City runs on a July 1 – June 30 Fiscal Year
  • Questions? Contact [email protected]