City Cemetery roadway and irrigation improvements

Project resources
Project overview
- The City Cemetery is generally between 11th Avenue and 4th Avenue, North Street and U Street. The project area is in the Cemetery’s northeast quadrant, generally located between 1040 East and 1200 East and 280 North and 11th Avenue.
- OVERALL PROJECT SCHEDULE:
- December 2024 – July 2026.
- We anticipate construction beginning December 2024, with some mobilization beginning November 25-27, 2024.
- The estimated completion date of work sequence one (about 80% of the work) is winter 2025.
- The estimated completion of work sequence two is summer 2026.
- Anticipated hours of operation will generally be 7 a.m. to 6 p.m. Monday through Friday and Saturday 7 a.m. to 2 p.m.
- **Schedule is subject to change depending on weather, permitting, and unknown circumstances.
- December 2024 – July 2026.
- GENERAL PROJECT WORK DESCRIPTION:
- Tree protection and SWPPP, demolition, utilities (roadway irrigation and plat irrigation), grading, curb and gutter, concrete paving, landscape restoration.
- Roadway improvements generally include replacing exiting roadway features with concrete pavement, curb and gutter, waterways, and street signs with decorative posts.
- Roadway area irrigation system improvements (roadway and roadway vaults and associated assemblies and electrical pipe, wiring, and controllers) generally include replacing irrigation with new irrigation system.
- Plat area irrigation system improvements generally include replace landscape irrigation and install new root watering system for trees, and related work.
Contact us
Contractor: M.C. Green & Sons, Inc
- Site Superintendent: Zach Justus
Owner’s representative: MOCA Systems, Inc
- Project Manager and POC: Brian Whittam
- Phone: 801-556-1570
- Email: brian.whittam@mocasystems.com
Salt Lake City:
- Architecture and Construction Management:
- Construction Project Manager: Hayden Barker
- Cemetery
- Phone: 801-593-5020
- Cemetery website