City Cemetery Roadway and Irrigation Improvements

Responsive Margin

City Cemetery roadway and irrigation improvements

Map of the City Cemetery Roadway Construction. The road is closed but accessible by foot from on Elm Street and 355 N from Cypress Ave to 1100 and on 325 E from 350 E to 1200 E. The road is closed with no access on 405 N from 1040 E to Cypress Ave, on Cypress Ave from 405 N to 330 N, and on 1200 E from 355 N to 324 E.

Project overview

The City Cemetery is generally between 11th Avenue and 4th Avenue, North Street and U Street. The project area is in the Cemetery’s northeast quadrant, generally located between 1040 East and 1200 East and 280 North and 11th Avenue

OVERALL PROJECT SCHEDULE

December 2024 – July 2026

  • Construction began December 2024, with some mobilization beginning November 25-27, 2024.
  • The estimated completion date of work sequence one (about 80% of the work) is winter 2025.
  • The estimated completion of work sequence two is summer 2026.
  • Anticipated hours of operation will generally be 7 a.m. to 6 p.m. Monday through Friday and Saturday 7 a.m. to 2 p.m.
  • **Schedule is subject to change depending on weather, permitting, and unknown circumstances.

GENERAL PROJECT WORK DESCRIPTION

  • Tree protection and SWPPP, demolition, utilities (roadway irrigation and plat irrigation), grading, curb and gutter, concrete paving, landscape restoration. 
  • Roadway improvements generally include replacing exiting roadway features with concrete pavement, curb and gutter, waterways, and street signs with decorative posts. 
  • Roadway area irrigation system improvements (roadway and roadway vaults and associated assemblies and electrical pipe, wiring, and controllers) generally include replacing irrigation with new irrigation system.
  • Plat area irrigation system improvements generally include replace landscape irrigation and install new root watering system for trees, and related work.