Salt Lake City Cemetery Improvements

Responsive Margin

Project Overview

  1. The City Cemetery is generally between 11th Avenue and 4th Avenue, N Street and U Street.  THE PROJECT AREA is in the Cemetery’s Northeast Quadrant, generally located between 1040 E. and 1200 E. and 280 N. and 11th Avenue.
  2. OVERALL PROJECT SCHEDULE:  December 2024 – July 2026.  We anticipate construction beginning December 2024, with some mobilization beginning November 25-27, 2024. The estimated completion date of Work Sequence 1 (about 80% of the work) is Winter 2025. The estimated completion of Work Sequence 2 is Summer 2026. Anticipated hours of operation will generally be 7 AM to 6 PM Monday through Friday and Saturday 7 AM to 2 PM. **Schedule is subject to change depending on weather, permitting, and unknown circumstances.
  3. GENERAL PROJECT WORK DESCRIPTION:  Tree protection and SWPPP, Demolition, Utilities (Roadway Irrigation and Plat Irrigation), Grading, Curb and Gutter, Concrete Paving, Landscape Restoration.  Roadway improvements generally include replacing exiting roadway features with concrete pavement, curb and gutter, waterways, and street signs with decorative posts.  Roadway area irrigation system improvements (roadway and roadway vaults and associated assemblies and electrical pipe, wiring, and controllers) generally include replacing irrigation with new irrigation system. Plat area irrigation system improvements generally include replace landscape irrigation and install new root watering system for trees, and related work.

Contact Us

Contractor | M.C. Green & Sons, Inc

  • Site Superintendent | Zach Justus

Owner’s Representative: MOCA Systems, Inc

Salt Lake City Corporation, Engineering Division

  • Construction Project Manager | Hayden Barker

Salt Lake City Corporation, Cemetery