Building Services & Civil Enforcement
801-535-6000
All Site Development Permit applications are submitted electronically through the Citizen Access Portal.
The fee for a Site Development Permit is $316.00 for the 1st acre & $61.00 each additional acre. General Requirements
- If the project requires the subdivision of land, provide a copy of the recorded subdivision plat.
- Site Development approvals shall only be approved in conjunction with a building permit application, stamped by a Utah State licensed architect or engineer which includes the following:
- a A vicinity map with north arrow.
- b Identification and description of the scope of work to be conducted on the site.
- c The number of cubic yards being brought into or removed from the site.
- d The address, tax parcel number and legal description.
- e The property lines along with the dimensions of each boundary.
- f All existing and proposed public way improvements and access points.
- g Grading plans with grades shown at a minimum of 2 ft intervals. Show existing grades with dashed lines & proposed grades with solid lines.
- h Drainage plans with calculations, drainage devices, showing drainage flows to and from the entire site.
- i Where soils need to be stabilized or where an existing building is adjacent to the area of site development work (excavation), provide a temporary shoring wall plan.
- j Utility plans, if utilities are being installed.
- k Erosion control plans.
- l Soils report.
- m Haul route as identified and approved by the Transportation Dept.
- n Wheel cleaning area in accordance with 18.20.210 of the SLC Ordinances.
- All grading over 5,000 cubic yards shall require professional engineering and be designated as “Engineered Grading”.