Salt Lake City Building Services Closeout Guidance
Updated 10/17/23
**This list is not intended to be all inclusive, additional documents/requirements may present themselves depending on the project**
- Arc flash calculations for main electrical service gear NEC 110.16
- Available fault current label NEC 110.24
- Address sign / building numbers / unit numbers IBC 502
- FDC / riser room signage IFC 912.2.2
- Stair signage both sides of stair shaft IBC 1023.9.1
- Egress map and area of refuge
- Two-way communication operational and approved IBC 1009.8
- Backup generator commissioning and special inspection report for bolting
- Egress lighting / exit signs approved as complete IBC 1008 & IBC 1013
- ADA egress components complete / signage / parking installed IBC 1103 & ICC A117.1.
- Ariel obstructions mitigated
- Fire extinguishers placed per plan and tagged IBC 906
- Dampers approved as complete IMC 607
- CO/NO detection and expulsion systems approved as complete IMC 404.1
- Systems interlocks approved as complete
- Finals approved for all areas for all MEP, fire, building or other permits.
- Phased occupancy plan (if applicable) submitted to Lead Inspector for review and approval by SLCFD Fire Protection Engineers
- All deferred submittals must be satisfied
- Landscaping complete
- Closeout documents received and approved (instructions found on second page)
- Upload all closure documents to the “inspections closeout documents” folder in PDOX of your primary building permit, do not upload to sub permits
- Test and balance
- TPO warranty (if applicable)
- Blower door test results 100% of building 250,000 sq ft. or less conditioned space and 25% units on buildings larger than 250,000 conditioned area per IECC 409.9
- Bac-T test (most remote fixture) IPC 610.1
- Back flow certifications for all devices culinary, landscape and fire – IPC 312.10
- Elevator certification State Requirement
- Boiler certification State Requirement
- Radio repeater testing, certification, or waiver as applicable from the Fire Prevention Bureau needs to be completed IFC510.5.4
- All other relevant documents and test results requested by the project inspector
- Final sign off of special inspections provided by 3rd party inspection company
- Do not upload regular SI reports to this folder it is for final closeout documents only.
Certificate of Occupancy
Signoff from transportation, engineering, and public utilities as applicable.
All the above listed items