Salt Lake City Building Services Closeout Guidance
**This list is not intended to be all inclusive, additional documents/requirements may present themselves depending on the project**
Last updated:
Electrical
- Arc flash calculations for main electrical service gear- NEC 110.16
- Available fault current label- NEC 110.24
- Backup generator commissioning and special inspection report for bolting
- Backup generator Hazmat permit as required by the Fire Prevention Bureau
- Radio repeater testing, certification, or waiver as applicable from the Fire Prevention Bureau needs to be completed- IFC510.5.4
Fire
- FDC / riser room signage- IFC 912.2.2
- Fire extinguishers placed per plan and tagged- IBC 906
- Ariel obstructions mitigated- IFC D105.4
- Two-way communication operational and approved- IBC 1009.8
Egress
- Egress map and area of refuge signage
- Egress lighting / exit signs approved as complete- IBC 1008 & IBC 1013
- Stair signage both sides of stair shaft- IBC 1023.9.1
- ADA egress components complete / signage / parking installed- IBC 1103 & ICC A117.1.
Mechanical
- Dampers approved as complete- IMC 607
- CO/NO detection and expulsion systems approved as complete- IMC 404.1
- Systems interlocks approved as complete
- Test and balance- IMC 608
Plumbing
- Bac-T test (most remote fixture)- IPC 610.1
- Back flow certifications for all devices culinary, landscape and fire – IPC 312.10
General
- Landscaping complete
- Address sign / building numbers / unit numbers- IBC 502
- TPO warranty (if applicable)
- Blower door test results 100% of building 250,000 sq ft. or less conditioned space and 25% units on buildings larger than 250,000 conditioned area per- IECC 409.9
State Requirement
- Elevator certification
- Boiler certification
Project Closeout
- Finals approved for all areas:
- MEP
- Fire
- Building
- Other permits
- Final sign off document for special inspections provided by 3rd party inspection company, engineers, commissioning agency, etc.
- Phased occupancy plan (if applicable) submitted to Phasing/TCO Team, which includes Fire, Public Utilities, and Building Services for review and approval prior to final inspections commencing
- All deferred submittals must be satisfied
- Closeout documents received and approved
- Upload all closure documents to the “inspections closeout documents” folder in PDOX of your primary building permit, do not upload to sub permits.
To gain access email [email protected] or call 801-535-7224.
- Upload all closure documents to the “inspections closeout documents” folder in PDOX of your primary building permit, do not upload to sub permits.
- All other relevant documents and test results requested by the project inspector such as commissioning reports of equipment/systems, etc.
- Do not upload regular SI reports to this folder, it is for final closeout documents only.
Certificate of Occupancy
- All the above listed items
- Signoff from Transportation, Engineering, and Public Utilities as applicable
- For Phased or Temporary Occupancy requests consult with project inspector for guidance early on in your project
- Certificates of Occupancies are posted to the Citizen’s Access Portal after issuance. Prior to submitting a request for a certificate, research Building Permit records to verify the document hasn’t already been processed. Certificate of Occupancies are posted under “Attachments” below the “Record Info” tab
- To submit a request for Certificate of Occupancy email [email protected]
Transportation, Engineering, and Public Utilities are separate departments and will need to be contacted individually for inspections and approvals. A Certificate of Occupancy will not be issued without their approval.
Transportation – 801-535-6630 | [email protected] | Jena Carver – 801-573-5058
Engineering – 801-535-7961 | [email protected]
Public Utilities – 801-483-6900 | [email protected]
Need Help?
Contact our office:
Building Services
349 S 200 E, Suite 400
Salt Lake City, UT 84114
Phone: 801-585-7224