Public Utilities

Customer Service: (801) 483-6900 | Report Emergency: (801) 483-6700

Beck Street Sewer Rehabilitation

Project Overview

Salt Lake City Department of Public Utilities (SLCDPU) operates and maintains three major sewer trunklines that carry all wastewater from across the City to the treatment plant. SLCDPU will soon begin rehabilitating its oldest sewer trunkline, which was originally installed in the 1890’s.

Most of the work will use trenchless construction methods and will take place at existing access manholes along Beck Street between 800 North and 1800 North. In some areas, the pipe will need to be replaced using open excavation. This project is necessary to ensure safe and reliable sanitary sewer service and treatment for many years to come.

What is the scope of this project?

For most of the project, the City will use newer technology to install a cured-in-place-pipe (CIPP) liner inside of the existing sewer main. The liner is installed through existing manholes, which helps reduce construction impacts compared to traditional trenching.

A 1,500-foot section of sewer pipe on Beck Street (US-189) will require a traditional open-trench replacement. During this work, drivers can expect intermittent lane closures, lane shifts, and limited left-turn access onto and off Beck Street within the construction area. More details will be provided soon.

Will I experience disruptions to my sewer service?

To keep sewer service operating during construction, crews will install a temporary bypass system. This system redirects sewage flow around the section of pipe being repaired. Pumps and temporary above-ground pipes will be used to keep wastewater flowing and prevent service interruptions, sewer backups, and environmental impacts during repairs.

While the bypass system is active, nearby residents and businesses may experience:

  • Temporary changes to access for sidewalks, roads, or driveways
  • Increased odors
  • Increased noise from pumps powered by generators

Construction Impacts

  • Construction work will usually take place Monday through Friday between 7 a.m. and 5 p.m.
  • We will notify residents prior to any potential driveway impacts, road closures, or detours.
  • At least one access point to each business will be always maintained. When needed, trenches may be covered with steel plates to allow vehicle access.
  • Residents should expect increased noise and dust during construction.

Contact

Timeline

Construction is slated to begin as early as March 2026 and conclude by December 2026.

Project Timeline

  • February 2026: Begin early community outreach
  • March 2026: Present at local community council meeting
  • March 2026: Start construction by cleaning and documenting the sections of pipe to be lined
  • April – June 2026: Complete CIPP lining from approximately 800 North to 1800 North
  • July – September 2026: Trenching operations on Beck Street to replace approximately 1500 feet of sewer pipe
  • October – December 2026: Complete remaining CIPP lining work and project cleanup, including asphalt restoration work

*Construction schedules are subject to change due to weather or other unforeseen circumstances.