East-West Water Line
Project Purpose
The 6-mile water line will provide an additional water supply to supplement existing wells in the Sugar House and Millcreek areas, as well as maintain SLCDPU’s standard of reliability while meeting future growth’s water demands in Salt Lake City.
The East-West Water Line will:
- Supplement Water Supply – This new aqueduct will provide a redundant water supply to replace or augment existing wells in the Millcreek and Sugarhouse areas.
- Maintain SLC’s Standard of Reliability – This new line allows SLCDPU to continue to provide reliable service in the event of a supply interruption or waterline break as well as expand service delivery in the Millcreek and downtown Salt Lake City areas.
- Meet Future Downtown and Northwest Growth Water Demands – As growth and redevelopment continue to increase water needs in the area, this aqueduct will help provide additional supply to Salt Lake City’s downtown and northwest quadrant.
Project Update: 2026
Phase 3 of the East-West Water Line project was completed in December 2025. Phase 3 is a segment of the 6-mile water conveyance line that will provide an additional water supply to supplement existing wells in the Millcreek and Sugar House area as well as maintain SLCDPU’s standard of reliability while meeting future growth water demands in the Salt Lake valley.
Anticipated Phases
Phase I – COMPLETE – 500 East from Coatsville Ave. to Ramona Ave.
Phase 2 – COMPLETE – Highland Drive to 900 East
Phase 3 – COMPLETE – Grace Street from 3300 South to 3075 East
Future Phases: Design and construction for future phases of the project will occur, depending on funding.

This map showcases the East-West Water Line project area, part of the Salt Lake City Department of Public Utilities’ commitment to serving customers and protecting the environment by delivering high-quality drinking water that exceeds EPA standards.
Contact Information:
Email: [email protected]
Phone: 801-849-3236